Calendars in Programming
In the Open Standard
Lo GaryMember for 16 years 8 months
- Created
- 2
- 5
0
Supposing the project duration is 300 calendar days and I use calendar with public holidays and weekend (assuming a 6 days work week) for scheduling of construction activities.
I scheduled to have a pour of concrete on this coming Saturday, but the consultant suddenly revised the drawings and the concreting had to be postponed 2 weeks later. Do i entitle the EOT on the Sundays or public holidays?
Gary
I scheduled to have a pour of concrete on this coming Saturday, but the consultant suddenly revised the drawings and the concreting had to be postponed 2 weeks later. Do i entitle the EOT on the Sundays or public holidays?
Gary