Lump sum prelim - EOT

Ronron MartinezMember for 16 years 10 months
Created
2
1
0
Hi, All

is it neccesary to furnish document for pre-lim EOT.

Regard’s
Cy

2 replies

Oldest first
  1. 0
    Samer Zawaydeh ·
    Dear Ronron,

    You need to read your Conditions of Contract (COC) and follow the procedural requirements. Otherwise you will be in violation of the COC and it will be harder to get what is entitled for you.

    With kind regards,

    Samer
  2. 0
    Shah. HB ·
    Hi Ranron

    In general clear and lucid presentation of Preli.EOT documents are essential for entitlement .