Hi Guys,

I need a piece of Advise. We work as a subcontractor. We are doing now the EOT request. Main Contractors QS asked us to submit cause & effect in Excel sheet. He keep on revising that and make it favorable on them. He said it will be their submission to client.Main Contractors QS said that our real submission (which shows too much delay on their side) will be internal only. I want to know if theres any effect on us? He asked me to make program that will show all the delays (he meant was entitlement program)but he is giving baseline target date. Is it ok to follow he’s instruction?Im afraid soon they will tell us that you agreed to us.

Regards,

3 replies

Oldest first
  1. 0
    Samer Zawaydeh ·
    Dear Mervilyne,

    Assisting your General Contractor because they can’t prepare their claim is one thing, and sending them official letters with your claim for the EOT is another thing.

    I recommend that all the communication that you send to the General Contractor be monitored by a senior in your team. Besides, they might charge this time to the General Contractor.

    Your EOT should be reviewed by your seniors before submittal. It has to be submitted in accordance to the CoC.
    Otherwise, you will find it difficult to prove unless you go to courts.

    With kind regards,

    Samer
  2. 0
    Mervilyne Panganiban ·
    Dear Sir,

    I always send it to my immediate superior, however, he keep on telling me to follow them. I’m afraid that soon everything will mess up and blame will be on me.

    Thanking you,
  3. 0
    Mike Testro ·
    Hi Mervilyne.

    You need to do two submissions:

    1. That which reflects your true sub-contract position.
    2. The one your main Contractor is asking for.

    You cannot do an EoT analysis on an excell sheet - you need a detailed critical path programme to impact events.

    As a sub-contractor you will need to combine two alaysis methods:

    1. As Built v As Planned to show the Main Contractors Delays to your sub-contract start dates.
    2. Impacted as Planned for all other delays to your sub-contract work.

    Good Luck

    Mike Testro

Log in or join to reply