work program revision in accordance with approved E.O.T

Mai TawfeqMember for 16 years 7 months
Created
4
4
0
Hi Dears:

when the project owner approved extension of time and contractor instructed to revised his plan accordingly :

which one of the following path should revised?

1. The target baseline .
2. Or the updated program considering the data date is the first date of claim arising .

Please advise.

Thanks with a best regards.


mai

4 replies

Oldest first
  1. 0
    Mike Testro ·
    Hi Mai

    Save the baseline in a new file - add in the delay events that caused the EoT to show the agreed likely completion date.

    Save the file as Baselie EoT 1 and use that file for future contract progress and updates.

    Best regards

    Mike Testro
  2. 0
    Mai Tawfeq ·
    thanks.
  3. 0
    Vond Kye ·
    Mai,

    It all depends on what approach youve used to claim EoT. If it is indeed Impacted as planned then Mike’s reccommendation will hold true. If another type of approach has been used to claim extension,then ur baseline will be in accordance to that EoT.


    Regards

    Vond Kye
  4. 0
    Mike Testro ·
    Hi Vand

    Welcome to PP

    Since the EoT was awarded while work is in progress the Impacted As Planned is the most likely method to have been used.

    The other 3 are applicable to Forensic Analysis.

    Best regards

    Mike Testro

Log in or join to reply