Hi Dears;
I need the kind opinions in the following case:
the project is (marina with resort) seven main contracts, one contractor has been given three contracts :
1. hotel .
2. 5 residential blocks (g+5) .
3. Infrastructure.
The owner stopped realizing the due monthly payments today the contractor is entitled to 24 millions .
The site is suffering delay and to be honest the delay caused by both party (owner with consultant) and (contractor).
And both parties are suffering problem in a cash flow.
My question is ;
What the recommended solution can be advised to the owner (the owner big VIP, without forgotten the contractor entitlement since he did the best level to meet the project directions, even with no money has been released since 4 months.
I forget to mentioned that the contract form is FIDIC 1987 fourth edition ,and clause 69.3 give right to the contractor to slow the site progress.
thanks.
mai
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?