General contract doubts

Shah. HBMember for 17 years 10 months
Created
6
2
0
Hi

What is back to back contract mean with main and sub contractor?

Is there any diffenece between nominated sub contractor and sub contractor selected by the main cotractor?

6 replies

Oldest first
  1. 0
    Mike Testro ·
    Hi Shahul

    Generally the term Back to Back Contract mean that the Sub Contractor has the same level of risks and benefits that the Main Contractor has with the Employer.

    It applies to Domestic Sub-Contracts as Nominated Sub-Contractors are usually less risky for the Main Contractor to employ.

    Best regards

    Mike Testro
  2. 0
    Shah. HB ·
    Hi mike

    Thanks .In addition ,do nominated subcontractor have back to back contract with main contractor?

    Will Nominated subcontractor have separate condtions of contract laid by employer ?
  3. 0
    Mike Testro ·
    Hi Shahul

    As always it depends on the contract.

    Usually the Main Contractor has a reduced responsibility for Nominated Sub-Contractor’s own defaults.

    This is why a true nomination is very rare these days - the Employer uses terms such as "Preferred" or "Named" to get the Main Contractor to enter into a Domestic sub-contract with what is in reallity a nominated sub-contractor.

    Best regards

    Mike Testro
  4. 0
    Shah. HB ·

    Thanks Mike
  5. 0
    Samer Zawaydeh ·
    Dear Shahul,

    The nominated subcontractor is part of the Conditions of Contract. The Client identifies a preferred source and they determined that they want the materiar or service to come from that source.

    The subcontractor on the other hand, is selected by the Contractor and submitted to the Engineer for approval.

    With kind regards,

    Samer
  6. 0
    Shah. HB ·
    Thanks Samer

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?