Specification b/w Main & Sub Contractor

Shah. HBMember for 17 years 10 months
Created
4
1
0
Hi to all

In back to back contract,Specification related Delays the method stated for analysis eg.Time impact analysis applies to main contractor alone or even sub contractor should follow the same procedure for doing delay analysis

4 replies

Oldest first
  1. 0
    Samer Zawaydeh ·
    Dear Shahul,

    It depends on the Conditions of the Subcontract agreement. You will need to follow the agreement between the Contractor and the Subcontractor.

    With kind regards,

    Samer
  2. 0
    Shah. HB ·
    Hi

    Thanks Samer.Let me check this one out .Anyways we have workshop on this issue
  3. 0
    Samer Zawaydeh ·
    Dear Shahul,

    There is a clause in FIDIC that calls for the financial records of payment made to subcontractor to works that were paid for by the client to be submitted upon asking for it.

    With kind regards,

    Samer
  4. 0
    Shah. HB ·
    Many Thanks Samer. I got it resolved