contracual ambiguity

Divakar BabuMember for 16 years 11 months
Created
4
3
0
can any boday give an example of contractual ambiguity ? also i requried details ,how you sorted out the ambiguty

4 replies

Oldest first
  1. 0
    Mike Testro ·
    Hi Divakar

    The most common form of ambiguity is where one part of the contract documents state something different to another.

    In most contracts there is a procedure to remove the discrepancy by pointing it out to the Architect / Engineer and asking for a ruling.

    Usually there is an order of precedence among the contract documents.

    As a general rule anything written takes precedence over anything printed.

    Best regards

    Mike Testro
  2. 0
    Shah. HB ·
    Hi Divakar

    You can look into some places where it would have stated as "satisfactory level"
  3. 0
    Gary Whitehead ·
    Another area of ambiguity is the use of ambiguous terms. Some examples could be:
    Reasonable
    Best endeavours
    In good time
    Sufficient
    Joint responsiblity
    Adequate
    good / high standard


    The best way to solve such issues is to include a precise definition of the terms in the contract, or agree one post-contract award as soon as the potential ambiguity is identified. A less effecive option is to define whose interpretation of such terms is final.

    Some of these terms will also have been tested in court, so you can use precedent as a guide.

  4. 0
    Samer Zawaydeh ·
    Dear Diva,

    Would you please let us know what Form of Contract are you using and what kind of project are you working on.

    With kind regards,

    Samer

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?