EOT Claim
In the Open Standard
Oliver MellingMember for 19 years 5 months
- Created
- 3
- 1
0
I have a programme that is in delay, partially due to our engineers rate of output and partly due to a change in the scope of the design works by the client.
This variation work to the design has now been completed and we are attempting to rectify the delivery milestones for manufactured components.
We have captured the cost of the extra design and estimated the impact of the cange on manufacture costs.
Against the baseline I have also worked out the EOT associated with the extra design and manufacture durations, which has been used as a basis for working out potential extra project management costs we will incur.
The client has agreed with the actual costs and estimate for the design and manufacture but says that it is wrong to expect them to pay for forecasted extra PM costs associated with EOT. (They believe if we recover they could lose out by paying us upfront for extra PM costs associated with the EOT)
Is it normal to only receive actual costs incurred for PM costs associated with an EOT?
(Im guessing everyone is going to tell me that is depends on what the contract say :D)
This variation work to the design has now been completed and we are attempting to rectify the delivery milestones for manufactured components.
We have captured the cost of the extra design and estimated the impact of the cange on manufacture costs.
Against the baseline I have also worked out the EOT associated with the extra design and manufacture durations, which has been used as a basis for working out potential extra project management costs we will incur.
The client has agreed with the actual costs and estimate for the design and manufacture but says that it is wrong to expect them to pay for forecasted extra PM costs associated with EOT. (They believe if we recover they could lose out by paying us upfront for extra PM costs associated with the EOT)
Is it normal to only receive actual costs incurred for PM costs associated with an EOT?
(Im guessing everyone is going to tell me that is depends on what the contract say :D)
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?