Skip to content

Variation and cost escalation

Harish GopalanMember for 18 years 1 month
Created
9
4
0
Hi all my company is doing PT works for a commercial complex and recently we found that there is an increase in quantities for beam and slab area so we submitted a formal letter explaining the actual situation with reconciliation of the bill.But the main contractor rejected the bill asking us to give mode of measurement of this part if the codes provide for the same or back it up with details of any similar other works wherein these areas were measured and certified for payment.Plus he has included a escalation clause in his letter saying that the claim for the price increase has to be backed up with proper documents like purchase vouchers etc.Earlier when there was price increase you were paid and if the prices come down the benefit has to be given for the client.Moreover he says that WCT is not applicable for subcontractor according to the local law.Even we are not eligible for the service tax.But when we approached the lawyer he is saying that we are eligible for service tax and has given a letter.we are planning to produce it to the client.Now i referred the fidic 2005 for subcontracting work clause 13.1 states that work can be varied only by the way of contractors instruction and the subcontract variations may be initiated only by the main contractor.Guess nothing is favorable for sub contractors?Kindly advice how to take it forward?

9 replies

Oldest first
  1. 0
    Satish Kumar ·
    Dear Harish,

    What do you mean by PT works? Do you adhere to FIDIC or is there any other contract between you and your client.
  2. 0
    Harish Gopalan ·
    PT is post tensioning work.yes we adhere to FIDIC edition is 1992
  3. 0
    Sudharma C. ·
    proving escalation cost is not easy but that does not mean it cannot be done, and most clients and engineers would ask u to prove there was a price escalation.

    u need to do some research on the national price index for that particular materials in that country to prove that was an escalation, ie when the contract was awarded and the price as it is now.

    certain types of contract has a mathematical formula in the conditions of contract on how to calculate the price escalation, if there is such a formula in your contract, go along that way.

    rgds


  4. 0
    Satish Kumar ·
    Dear Harish,
    If there is an increase in quantity without any increase in scope or alteration of scope and if you are sure that the way you measure the quantities is correct-as per the terms of your contract or as per prevailing industry practice, you provide the code pertaining to the method of measurement; There should have been an error on the part of the Client in arriving at the BOQ estimate.

    Alternately, if there is an increase in the scope, the client should have instructed you by way of a letter, MOM or a verbal instruction which you should have confirmed or yet to confirm, with reference to that take forward the proposal for variation.

    Regarding escalation:

    Refer your COPA (Conditions of Particular Application) for Escalation, first look whether you are eligible for Escalation, if yes then check in which way. If no formula is provided and nothing else is said about it for arriving at escalation, but if the contract speaks only that you are eligible for escalation, check whether you have provided a rate breakup to the client for the rates quoted by you during the tender stage and compare the present rates with them and claim the difference.

    Regarding WCT and Service Tax:
    Why are you worrying about WCt and Service tax, they are anyhow not yours but the governments!?, ask your contractor to give the same in writing and produce the same where required. However, check whether you have stated that service tax is extra in your quote? If you did not quote and further if you did not provide the rate breakup to your client at tender stage, he may assume that the same is deemed to be included in the quoted rates.

    Hope this helps to a certain extent, All the best.

    Regards,
    K
  5. 0
    Harish Gopalan ·
    Thanks a lot sathish actually there is nothing mentioned about the escalation formula ...Service tax is extra in our quote...If you could explain me how to derive the formula for escalation it would be really helpful.
    Actually there is one more problem with the contract and this has been identified long time back...The contract is back to back in the sense...If the client pays the GC then only he will pay to us...But every time he has been telling that clients hasn’t made any payments!!!Now how to go ahead..
  6. 0
    Satish Kumar ·
    Dear Harish,

    Make yourself clear on the following points:

    1) Are you eligible for Escalation, if the contract says ‘yes’ then the method should also be mentioned in it. If not by way of a formula atleast it will state something regarding it.

    2) Is there any point in your contract stating that the contract is back to back, i.e., if only client pays then the GC pays? If that is the case you request your GC to provide the formula that is mentioned in his contract with client for arriving at escalation. So that there will be uniformity.

    3) As a last recourse Escalation can be arrived at as follows:

    Step 1: arriving percentage of components
    Suppose you have the following components involved in your work : Labour, Material, Plant & Machinery.

    Now, based on the rate analysis of the rate quoted at the time of Tender workout the cost involvement of each component.

    Based on the scope of Work try to estimate costwise the % of each component:

    Say your Project cost is 100. Removing profits and Overhead component say 15%, the cost price of work components is 85.
    Say by your total estimate with your tender rates you obtained the following percentages Labour cost =10%, Fuel Cost = 10% (fuel cost is important in India), Material Cost = 60%, P&M cost=20% (total making 100%); ……..(1)

    now you can safely regard that for a given amount of work during a month (period) the above arrived percentages of cost will give you the approximate cost involvement of each component.

    By way of illustration suppose work done during july 2010 is Rs. 200, labour component cost will be 0.85x200x10%.
    for specific materials such as M1 (say, Steel), M2 (say, Stainless Steel ) and M3 (for materials other than steel and stainless steel).

    Assess the quantity of steel consumed during the month and then calculate the cost using the basic rate quoted during tender for steel, say cost is Rs. 20
    The cost percent of steel during the month is S = 20/200=10%,

    Following the same lines calculate for Stainless steel, say SS = 10%, then the percentage contribution of other materials would be 60-10-10 = 40% from (1) since total material component percent is 60%.

    Now 0.85x 200x60% of work done will be material component, but instead of using 60% directly adopt individual % , as explained above, for each material you want to claim and deduct the same from Total material % to obtain other material percent.

    .................................................
    Step 2: Escalation formula:
    Escalation amount = [100%-B]xWx ∑ [(Ai-Aoi)/Aoi]xPi,

    Pi is the cost percentage (as derived above) of component use the same % every month for all (labor, fuel, P&M ) except for materials. For materials Pi should be calculated each month based on consumption.

    B=Percentage of Overheads and profits, 15% in the above case

    W= work done during the month

    Ai is the index of component 28 days prior to the billing month, alternately, if you go by rates Ai will be average rate calculated based on the invoices in First in First Out (FIFO) order. Whether you go by rates or index adhere to the same in Ao and Ai

    Ao= Index/ Rate 28days prior to the submission date of Tender;

    A is the component for Escalation, say, Labour, steel, other materials, Plant & Machinery etc.

    for index use national index where available or a standard manufacturers rates (whose source approval is available with you and whose material you are using).

    Pi is the percentage of that component costwise (as explained above, except for materials other components can be arrived based on total estimate workout, however, It all depends on how sensitive the basic rates are in that country and how they affect your price - the choice should be made judiciously)

    Hope this helps.
    Regards,
    K
  7. 0
    Harish Gopalan ·
    Dear sathisH let me first thank you for patiently replying to my thread...We attented a final meeting regarding the issue and finally the client has instructed us do a remeasuremnt and submit the same to to the GC and thus there will be a prompt solution for these issues.
  8. 0
    Samer Zawaydeh ·
    Dear Harish,

    It is very important that you adhere to the procedural requirements of FIDIC, if you want to be compensated according to FIDIC.

    Please remember that you have to submit your complete claim analysis with supporting documents and total amount within 28 days from the end of the event.

    You have a difficult situation, because chances are you don’t have a copy of the GC contract, and you have no way of knowing what are the CoC of that Contract! Unles your contract is specific to the Back-to-Back clauses of the GC contract with the Client.

    With kind regards,

    Samer
  9. 0
    Bhimana Anand ·

    Dear Sathish, Everything you

    Dear Sathish,

     

    Everything you explained is beautiful.

     

    The formula for Escalation amount = [100%-B]xWx ∑ [(Ai-Aoi)/Aoi]xPi, is not clear

    what Ai    , Aoi   stands for ?

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?