How deep the WBS shall be put in to the EPC contract
- Created
- 3
- 4
All, reference to the forensic claims analysis, it is known that the main basis of the claims shall be refered to the Contract it self as legally binding by both parties.
I've found some EPC contract (particularly in the Lump Sum type of contract) noted that in the Contract Schedule only attached some milestones and put the Delay Liquidated Damages (LD) on the main Milestones such as : Final Acceptance of the works etc..
The schedule which was attached on the Contract document is only showed the WBS until level 2 (High Level schedule)
(Level 0 - Project, level 1 (E,P,C,I) , Level 2 Contract Object / Unit ).
My question is how deep the appropriate WBS to be putted in to the Contract Schedule (levle 2/ 3 or higher) ?
Thanks in advance for your responses....
Alex Iskandar
Indonesia
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?