Skip to content

How deep the WBS shall be put in to the EPC contract

Alex IskandarMember for 22 years 9 months
Created
3
4
0

All, reference to the forensic claims analysis, it is known that the main basis of the claims shall be refered to the Contract it self as legally binding by both parties.

I've found some EPC contract (particularly in the Lump Sum type of contract) noted that in the Contract  Schedule only attached some milestones and put the Delay Liquidated Damages (LD) on the main Milestones such as : Final Acceptance of the works etc..

The schedule which was attached on the Contract document is only showed the WBS until level 2 (High Level schedule)

(Level 0 - Project, level 1 (E,P,C,I) , Level 2 Contract Object / Unit ).

My question is how deep the appropriate WBS to be putted in to the Contract Schedule (levle 2/ 3 or higher) ?

Thanks in advance for your responses....

 

Alex Iskandar

Indonesia

3 replies

Oldest first
  1. 0
    Daniel Limson ·

    How deep the WBS shall be put in to the EPC contract

    Hi Alex,

    On forensic claims and your subject question, normally you need to proved or demostrate on the programme on how the event or events (if mulitple) has impacted the programme / project completion date or any milestones subject to LDs and this will largely depend on how deep or detailed your approved baseline programme is.

    Regards,

    Daniel

  2. 0
    Moe Barkouky ·

    what does the word forensic

    what does the word forensic mean? is it a legal term? i worked my life in claims but never heared of the word forensic claims.. i know that forensic means debatable .. but i mean is it a new expression?

     

     

    Thanks

     

    Moe

  3. 0
    Mike Testro ·

    Hi Alex It all depends on

    Hi Alex

    It all depends on whether the Contract Programme is incorporated as a Contract Document.

    Usually the Contractor agrees to complete the Works in an agreed period - that is a Contract Term.

    Outside of the Contract he then submits a contract programme which describes how the dates are to be met.

    It is unusual for the Programme to be incorporated as a Contract Document - if it is then all sorts of contractual shenanigins occur when a change order requires a change in the programme.

    Unless your are in the NEC family when changes in the programme are accomodated.

    As to the level of detail I would suggest you read some of my earlier threads - search on "Planning Abominations" to get the drift - all submitted programmes should be level 4.

    Best regards

    Mike Testro

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?