When should be the data date/cut-off date for Impact Programme
- Created
- 4
- 2
The contract completion date for our project has already passed. But due to some delays (our own delay and client's delay) and additional works (which cannot be linked to any of the contract works since these are independent to the original scope), we haven't finish the project yet. I was asked to make an impact programme to show the delays we encountered and the probable completion date of the project. My question is, when should be the data date for the impact programme? At the original contract completion date? At the latest update of the baseline programme? Or should I used as-planned impacted? Anyone can advice me? Thank you.