How to model delays in a single activity, caused by MULTIPLE resources
- Created
- 10
- 6
Dear All,
At the outset, let me apologize if this is in the wrong section. This is my first post, and as such, am new to this wonderful board.
I have a unique problem and I was wondering if someone kind enough can assist me in resolving it. I don't mind a solution for P3 or P6, as long as it works.
Here is the issue:
1. Let me say that my entire project has only 1 activity. Activity A (its just an example) that spans 1 month.
2. 2 resources are on that activity: Resource X and Resource Y (both are humans who will work on this project)
3. Now, what happens is that Resource X is unable to contribute for 10 days. And Resource Y is unable to contribute for 3 days (assuming this activity is not resource dependent, and assume that the resources were sick or cuold not come to work etc.)
4. Now, obviously, the schedule has stretched from 30 days to
30 days + 10 days delay due to Resource X + 10 days delay due to Resource Y (a simplistic example)
5. I am assuming that both Resource X and Resource Y are doing discrete work, that is work they do is not dependent on each other, not does it overlap at any point in time.
6. My quesiton is: Is it possible for me, to get a report (again, either P3 or P6, preferably P3) that tells me that the total break in Activity A (originally 30 days, now delayed by 13 days) is actually due to Resource X = 10 days delay and Resource Y = 3 days delay? I mean, can I get it ina tabular form? Or any other form?
7. If this is not available in P3 or P6, is there an ALTERNATE way of doing this? (I don't mind a workaround, as long as I get a rerpot that tells me which resource caused how much delay in which activity, assuming multuple resources are being delayed in a single activity -- this is VERY important)
8. I ALSO do not mind if someone can suggest an ALTERNATE software OR and addin (again, for P3 or P6 or even standalone program) that can do this (actually, record this and report)
Thanks in appreciation in advance
Regards,
L_H
10 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?




