As Built Schedule Preparation
- Created
- 2
- 2
Hello,
In major construction Projects, after the initial base line is approved, extension of time is being accorded many times according to delay events and revised schedule continues to be submitted and approved. Some activities in the initial baseline schedule are at very high level and in subsequent schedules these are being broken down. To summarise the current revised schedule being used is very much different from the initial base line schedule.To prepare an as built schedule for claims analysis, should it implemented on the current revised schedule or on the initial baseline schedule.The project is still in progress and yet to be completed.
I strongly feel the asbuilt dates are to be implemented on the current revised program.
Thanks in advance.
2 replies