EOT Claim over GANTT schedule.
- Created
- 3
- 1
Good day, this is the case:
The contractor is claiming 274 days EOT on a 382 days schedule from NOV2005 to DEC2006. The baseline schedule is a Gantt chart, I.E. not even SS or FF links or lags, just the gantt chart made in excel.
The question is, if the contract was entitled without a CPM schedule, how can you prove if there is right for extension of time? And if there is right, how do you quantify the amount of impact?
I am thinking of adding logic to the Gantt chart based on one annex of the contract which specifies the sequences of construction, But I also wanted to know some experts' opinion on this topic.
Best Regards,
Carlos.