Skip to content

Abortive Works

Lo GaryMember for 16 years 8 months
Created
5
3
0

It is very common that discrepancies are found between drawings.However, if discrepancies are not found and the contractor built something according to either one of the drawing.After that  the contractor found the discrepancies and were told that the works should follow the other drawings. Could the contractor claim for abortive works . It is usually the consultant would say the contractor is obliged to notify him the dicrepancies found and ask for instruction.  

5 replies

Oldest first
  1. 0
    Anoon Iimos ·

    i supposed there are always

    i supposed there are always QA/QC inspectors and specifications that govern over drawings, so if the contractor is in doubt, there will always be time for inquiries and decisions

  2. 0
    Gary Whitehead ·

    Obviously this will depend on

    Obviously this will depend on the precise wording of the contract, and the precise events which occured, but in general:

     

    1) A contractor can be expected to notify client of any discrepancies which he discovers and wait for instruction

    2) A contractor cannot be expected to check every single drawing issued for discrepancies. It is the client / design consultant's responsibility to provide the correct drawings.

    So yes, a contractor could probably claim for abortive works.

  3. 0
    Mike Testro ·

    Hi Lo If the building is fit

    Hi Lo

    If the building is fit for its intended purpose then the employer has not suffered any damage.

    It would be unreasonable therefore to insist on full restoration.

    If however because of the discrepancy the employer cannot make beneficial use of his building then restoration would be reasonable.

    As to who is responsible that is a problem for the courts but to my mind the discrapncy was in the design and that is where the blame trail should start.

    Best regards

    Mike Testro

  4. 0
    Adrian Nicholas ·

    In Most Cases, the Contractor

    In Most Cases, the Contractor in many cases should be able to claim for corective or change of scope works based on inital AFC drawings issued by the employer but normally there is an independent verify appointed in the project to make sure this does not happen.

  5. 0
    Andrew Flowerdew ·

    Gary is correct when he says

    Gary is correct when he says it depends on the wording of the contract and circumstances that occurred.

    For example, in D&B or EPC contracts I have seen more use in recent years  of a time period at the beginning of the contract within which the Contractor must inform the Employer, (Engineer), of any and all discrepancies in the drawings and if the Contractor fails to do so, the risk of abortive work etc then lies with the Contractor.

    In a more traditional Employer design, contractor build only scenario then the costs would usually be recoverable.

    The answer is in the contract, (hopefully).

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?