Abortive Works
In the Open Standard
Lo GaryMember for 16 years 8 months
- Created
- 5
- 3
0
It is very common that discrepancies are found between drawings.However, if discrepancies are not found and the contractor built something according to either one of the drawing.After that the contractor found the discrepancies and were told that the works should follow the other drawings. Could the contractor claim for abortive works . It is usually the consultant would say the contractor is obliged to notify him the dicrepancies found and ask for instruction.
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?