How to deal with Bad Records

Aidan KellyMember for 15 years 5 months
Created
2
2
0

Hi all

 

Ive been asssigned onto a civil project that is approx 50% complete and has no approved or logical baseline (open ends, hanging activites and unapplicable activties).

Records to date have been inaccurate. The entire management structure has been changed and i've assigned to compile change orders for extra scope, disruption and EOT. Change order is the only mechanism in the contract for cost/time increase.

For EOT demonstration has anyone got some advise on dealing with poor records?

The current recovery/forecast schedule (level 4) has absorbed all the delays to date without culpability or payment to contractor (us). Most of the delays are underground obstructions, change in working methods and procedures.

Would a very theoretical approach suit in this case?

Regards


Aidan 

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Aidan In other words

    Hi Aidan

    In other words -situation normal.

    Since your programme is currently unapproved I would start from the original programme before any progress updates and then tighten up the logic and removing all constraints - try to establish a clear critical path.

    Make sure you do this BEFORE making a detailed study of the delay events.

    Hint - this is done much quicker if you open up the .xer file in PowerProject - make the adjustments and save it back as an .xer for P6.

    Then make a spreadsheet log of all your change orders and make a chronological list of dtate of event impact of the events - that is the earliest possible date that the affected task could have started.

    Now create dummy tasks of each event in turn and impact it to the affected task - reschedule and note the effect.

    Go on to the next delay event and repeat the process.

    Make sure that all contractor's delay events are included in the matrix.

    This will establish your entitlement to any EoT.

    Disruption is a totally different matter and you will need a fully resourced baseline programme before you even think about it.

    Check other threads on the topic anmd come back if you need more help.

    Best regards

    Mike Testro

  2. 0
    Aidan Kelly ·

    Thanks Mike for the

    Thanks Mike for the tips.

    Baseline is not resourced but the disruption or more accuately described as lost/unproductive hours is quantifiable as it is mainly the delay in issuing permits resulting in idle time.

    Will look up other threads on this.

    Regards

    Aidan

     

     

     

     

     

     

Log in or join to reply