Delay Event - Calendar Day or Working Days

Shah. HBMember for 17 years 10 months
Created
3
3
0

Hi 

Please advise

Contract period for MEP Scope of works mentioned as calendar days and there is a letter from the client which states Friday is off applicable to all contractors on board,in this case the impact of delay event should be calculated as calendar days or working days

 

Regards

Shahul

3 replies

Oldest first
  1. 0
    Gary Whitehead ·

    Shahul,   can't you just

    Shahul,

     

    can't you just adjust all your labour calendars to have Friday off, re-run your schedule, and this will tell you your EOT claim?

  2. 0
    Mike Testro ·

    Hi Shahul It is important to

    Hi Shahul

    It is important to differentiate the difference between calendar and working days wjen describing cause and effect of a delay event.

    The duration of a delay event could be either a working or calendar day duration depending on the nature of the event.

    If it is a delay arising from a late preceding activity that is already on the programme then it should be the same calendar as the delaying task.

    If it is a late delivery of materials that is not on the programme then a 7 day week calendar would be more appropriate.

    The delay effect is always expressed in calendar days.

    Best regards

    Mike Testro

  3. 0
    Shah. HB ·

    Many thanks to

    Many thanks to all

     

    Cheer's

    Shahul