AACE 29r-03 - What is a 'Discrete Delay Event'?
In the Open Standard
Carlos AranaMember for 17 years 4 months
- Created
- 6
- 4
0
Page 81 of AACE Recommended Practice 29r-03 "Forensic Schedule Analysis" reads:
2. Cause of Delay vs. Effect of Delay
[last paragraph]
The best practice that incorporates the best features of both theories is to use the cause theory where discrete delay events exist and to use the effect theory where there are no discrete events that led to the delay. But note that in many cases the identification of discrete causes is a function of diligence in factual research, which is in turn dictated by time and budget allowed for the analysis.
I am wondering, what is to be understood as "Discrete event"? How do I identify it?
Saludos,
Carlos Arana.