Skip to content

AACE 29r-03 - What is a 'Discrete Delay Event'?

Carlos AranaMember for 17 years 4 months
Created
6
4
0

 

Page 81 of AACE Recommended Practice 29r-03 "Forensic Schedule Analysis" reads:
 
2. Cause of Delay vs. Effect of Delay
[last paragraph]
The best practice that incorporates the best features of both theories is to use the cause theory where discrete delay events exist and to use the effect theory where there are no discrete events that led to the delay. But note that in many cases the identification of discrete causes is a function of diligence in factual research, which is in turn dictated by time and budget allowed for the analysis.
 
I am wondering, what is to be understood as "Discrete event"? How do I identify it?
 
Saludos,
Carlos Arana.

6 replies

Oldest first
  1. 0
    Carlos Arana ·

    Posts should be editable,

    Posts should be editable, where did all my <enter> go? Here's it again hoping that it reads adequately:

     

    Page 81 of AACE Recommended Practice 29r-03 "Forensic Schedule Analysis" reads:

     

    2. Cause of Delay vs. Effect of Delay

     

    [last paragraph]

     

    The best practice that incorporates the best features of both theories is to use the cause theory where discrete delay events exist and to use the effect theory where there are no discrete events that led to the delay. But note that in many cases the identification of discrete causes is a function of diligence in factual research, which is in turn dictated by time and budget allowed for the analysis.

     

    I am wondering, what is to be understood as "Discrete event"? How do I identify it? Saludos,Carlos Arana.

  2. 0
    Mike Testro ·

    Hi Carlos In this sense

    Hi Carlos

    In this sense Discrete is opposite to Concrete.

    Concrete is an amalgum - a mixture where - Discrete is a standalone item.

    Best regards

    Mike Testro

  3. 0
    Gary Whitehead ·

    http://www.lmgtfy.com/?q=disc

  4. 0
    Ken Sadler ·

    "Discreet" is the opposite of

    "Discreet" is the opposite of "aggregate".

    Delay claims often attempt to desribe a number of delay events and then suggest that the effect of all those events together (i.e the aggregate effect) proves entitlement to the EOT sought.

    The problem with this is that it ends up being a global claim.  This is contrary to common law.  If you say that events A, B, C, and D together caused a delay but you can't say which one caused what amount of delay, I would say that I cannot actually determine what the charge being made against me is.  What did I do which entitles you to the EOT you claim?  If you can't tell me by separating the causes and effects, there is no case.  That's why global claims have to fail.

    JCT 05 and other contracts are clear on this but it is subtle.  Clause 2.27.2 (Notice by Contractor of delay) refers to in respect of each event identifed in the notice, the contractor shall......give particulars of its expected effects....

    It is necessary to isolate each event and to attribute the effect to each one separately.

    This is known as the discreet effect of the event as opposed to the aggregate of all the events put together.

    Regards

    Ken Sadler

  5. 0
    Mike Testro ·

    Hi Ken What about Doyle v

    Hi Ken

    What about Doyle v Laing?

    Best regards

    Mike Testro

  6. 0
    Ken Sadler ·

    Hi Mike,Doyle v Laing was of

    Hi Mike,

    Doyle v Laing was of course a Scottish case but it was referred to and given more formal English approval in London Underground v City Link in 2007.  There may be others later than this - not sure off the top of my head.

    That said, even though global claims appear more acceptable from these cases, success is still the exception rather than the rule.

    In London underground it was made clear that  success was really only to be considered "provided that sufficient convincing evidence is presented in respect of individual elements of a claim, those individual elements may succeed and a claimant may recover some of the losses it has claimed even though the claim does not succeed in its entirety".

    In any case, this is not a licence to submit lazy global claims - it is still necessary for the claimant to show that it is not practicable to show the discreet effects.  Moreover any events which are not the employer's risk have to be properly extracted.

    As always, it depends on the circumstances of course

     

    Regards

     

    Ken  

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?