Actvitity Durations
In the Open Standard
John KellyMember for 15 years 3 months
- Created
- 3
- 4
0
Hi Guys & Gals,
I am in the process of ensuring my Baseline is robust enough for a delay analysis, adding missing logic links, removing constraints etc. I have removed a lot of 'As late as possible' constraints that had no Predecessor and linked them with the relevant lag to a Start milestone.
Problem is when i add the FS +lag to each activity the start date is the same, Duration is the same but the Finish date is always a day earlier, all calendars are the same so its not that.
Any ideas? I am using P7 by the way
Thanks in advance