Delay Analysis using Impacted As Planned Method
In the Open Standard
Prageeth ChandrasiriMember for 15 years 3 months
- Created
- 2
- 5
0
Hi,
If you can, please give me some advice regarding this Delay Analysis Problem. I used “Impacted As Planned” method to analyses delays.
For the very first delay Event, I just took the Baseline & Impact the Delay into that. Now, my Problem is for the Next Delay event, should I use the Baseline or Already Impacted Programme to demonstrate the Delay Analysis.
Thank You