Creating TIA
- Created
- 9
- 4
Hi Every one,
Quick question. I have received a Time Impact Analysis from the Contractor who has used Baseline Schedule to show the impact of a delay which he thinks has been caused by the Owner. However, the project schedule has already gone through two (2) updates and Contractor has made a number of sequencing (logic) changes which were not contested (was accepted) by us. Now the question is should'nt the Contractor be using the latest update to show impact of the Owner activity delay as the plan has changed and agreed upon?
I will appreciate an early response if possible as I am in the middle of analysing their claim.
Best Regards
Meraj Zia