Apportionment of Delay
- Created
- 6
- 1
Hi
To assign delay responsibility between the owner and contractor in windows analysis how is mitigation best dealt with?
No investigation has been carried out as yet so this is just an rough exercise.
To assign the number of days delay caused in the month to the party with driving activities produces a higher number of days delay than the final window shows as throughout the windows there has been some mitigation.
Is it best to just assign an arbitrary number to each month, ie tally all the windows at the end and see who is responsible for more.
If anyone has any examples or further reading on this it would be of great help.
Many thanks.