Variation Clause
In the Open Standard
Sankar VijayanMember for 16 years
- Created
- 8
- 4
0
Dear Sir,
Variation in quantity of a particular Work pakage exceed more than 25% the impact on Contract Value is Only 1%
Can we revise the rate ? or this a not claimable since the Contract value didnt change by 25%
Our Contract says the following
In case the Contract Price varies by more than plus or minus 25% .The Contractor may claim revision of rates The revision of rates shall apply only to quantities in excess of 25% or short by 25% provided the aforesaid condition regarding overall variation in contract price is met with.
Thanks& Regards
SV