Calendar to be used for evaluating the impact of delay event

Ammar Al-SaketMember for 15 years
Created
3
3
0

3 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Ammar Retain the working

    Hi Ammar

    Retain the working calendar for the impacted tasks.

    The shift of the end date demonstrating delay should be represented by a hammock which has a 24/7 calendar.

    The impacted events in the fragnet may have different calendars as required.

    Best regards

    Mike Testro

  2. 0
    Ammar Al-Saket ·

    Thanks a lot Mike,Just to

    Thanks a lot Mike,

    Just to make sure that I've understood you correctly; say I have the following situation:

    • project has 3 activities namely: A,B & C linked Finish-to-Start relationship.
    • activity D is the project completion "finish-milestone".
    • calendar used for all activities is 5 working day calendat
    • Time for Completion of the Works is counted in calendat days
    • An excusable and compensable delay event had delayed the completion date of the project (milestone D) for 4 weeks (20 working days) 
    • So, is the compensation for 28 days or for 20 days?

    Thanks again

    Ammar

  3. 0
    Mike Testro ·

    Hi Amar 28 calendar

    Hi Amar

    28 calendar days.

    Best regards

    Mike Testro