How to make a fragnet of activities in primavera P6? What exactly does the word "fragnet" mean in this context?
The fragnet is supposed to consist of subset of activities in the project schedule directly related to the schedule. Fewest number of activities and relationships can be added to reflect this delay on the schedule. Existing relationships and are supposed to be left intact whereever possible even if redundant unless their retention would negate the actual work restraints on the project.