Engineer Not Responds EoT Claim Until the Revised Finish Date
- Created
- 3
- 1
Dear All
1- The Revised Finish date is 02-02-YYYY
2- An EoT claim submitted by the contractor on 01-01-YYYY
3- Engineer’s letter to submit Recovery Program (FIDIC 1999) clause 8.3 & 8.6 on 03-01-YYYY (after the submission of EoT and 30 days before the revised finish date)
4- Many of the material have not been delivered by a Third Party until the Data Date, while the Employer has sent numerous reminders.
5- The remaining work is not possible to finish in the time from the Engineer’s letter to the Revised Finish Date even with the double of manpower and 24 x 7 operations.
6- Data date is 01-03-YYYY
Q-1 Is the Engineer’s letter logical?
Q-2 what is the status of the Revised Finish Date on Data Date?
Q-3 LDs are due by the Data Date?
Need experts’ comments
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?