FIDIC Clause 20.1
- Created
- 4
- 1
Hi All
I have doubt in FIDIC 1999 clause No. 20.1 “Within 42 days after receiving a claim or any further particulars supporting a previous claim or within such other period as may be proposed by the Engineer and approved by the Contractor.”
The clause can be interpreted as
“Within 42 days after receiving a claim or within 42 days any further particulars supporting a previous claim or. . . “
Please clear my doubt
What if the Engineer asks for a meeting / workshop to the contractor on the 38th day of the submission of the contractor’s interim claim and says that 42 day shall be counted from the date of the meeting / workshop. And rejects the claim after 72 days after the submission of the claim
Cheers - Tanveer
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?