When to put forward an EOT claim in case of ongoing Employer Risk Event
- Created
- 3
- 4
Dear All,
I would like to know that is it correct to submit an EOT even before the conclusion of an Employer Risk Event? In the project I am working on there has been a delay in the delivery of one of the Client supplied material. The installation of the same item is on the critical path as per the approved Baseline programme. As of the information at hands, it may take another 3-4 weeks before it reaches the site. In the meanwhile notification for the delay has already been send to the CR.
So, can we submit an EOT claim now or it's better to wait for the actual delivery of the item in order to have complete information about the delay caused?
Best Regards,
Kaif Mohsin