Dear PP,

Good day to all. I am having some ambiguity regarding the proper way in analyzing the claims for EOT. I just want to know your opinion if we need to correct the out of sequence activities prior to window analysis?

Your expertise with this matter is highly appreciated.

 

Regards,

Ritchie

1 reply

Oldest first
  1. 0
    Mike Testro ·

    Hi RitchieMy advice is that

    Hi Ritchie

    My advice is that as and when you come to a window where an adjustment is needed you do it then.

    You will have to save the baseline each time you make an adjustment.

    My better advice is don't bother with a windows analysis for a forensic situation - it is a waste of time.

    Best regards

    Mike Testro