As bulit but for
- Created
- 13
- 1
13 replies
Oldest first- 0MTMike Testro ·
Hi TimAs Built but for and
Hi Tim
As Built but for and Collapsed as Built are synonimous.
The system is applied if there is not a viable responsive baseline - you only need a start and finish date.
The method assumes that all the periods of delay are within the As Built programme so if the delay periods are removed the As Built will collapse to where is should have been but for the delay.
The method is easily challenged because the analyst has to put a critical path into the as built data and one guess is a good as. another. This also assumes that the As Built records are good enough to start with.
I avoid the method entirely.
Best regards
Mike T.
- 0MTMike Testro ·
Hi GustavMost times Good is
Hi Gustav
Most times Good is not good enough.
Ideally the records should state Who did What Where and When at weekly intervalls and linked to the task UTID.
This rarely happens - at best you can ascertain when a task starts and finishes.
In a forensic situation this is usually good enough for a Time Impact Analysis.
Best regards
Mike Testro
- 0AAAnders Axelson ·
"As-built but for" and
"As-built but for" and "as-built collapsed" (ABC) mean the same thing. They refer to a method whereby delay is calculated by measuring the change in project duration after subtracting representations of delay events on the backward pass.
"As-planned impacted" (API) is the equivalent method whereby delay is calculated by measuring the change in project duration after adding representations of delay events on the forward pass.
ABC ignores the original as-planned schedule. API, equivalently, ignores the as-built schedule.
In a tort case, where there is no planned schedule, and the relevant comparison is actual (if tort did not occur) versus actual (given tort did occur) ABC is more likely to be appropriate.
- 0AAAnders Axelson ·
Mike,The critical path is
Mike,
The critical path is more than you need on an As-Built Collapsed. The critical path is determined by a forward pass and then a backward pass. With the ABC, however, you only need to calculate the longest path length on the backward pass. You do not need a forward pass at all. Similarly with the API and the time impact analysis, you only need to know the longest path length on the forward pass; you don't need to perform a backward pass at all.
Strictly speaking, the ABC, the API and the TIA are not true critical path-based methods, as they only deploy one of the two passes!!
(...That's in the absence of resource levelling, btw. If you have resource levelling, you may still make use of float calculations to determine the levelling priority, which requires both passes...).
- 0AAAnders Axelson ·
Yes, Mike, that's very true.I
Yes, Mike, that's very true.
I believe the ABC method was originally conceived for hand-drawn ADM (Arrow Diagramming Method), AOA (activity-on-arrow) or AON (activity-on-node) networks. A claimant or architect/engineer would just write the numbers for a revised backward pass in a red pen over the as-built data, and then two sets of numbers could be compared. (The various editions of the textbook by Antill & Woodhead - which I think is probably still one of the best textbooks on construction scheduling even though its first edition was in 1970 - are very good on this).
Conventional modern software like Primavera, Microsoft Project etc., however, does not lend itself readily to this method because the as-built data left of the data date is "dead" and so it has to be reconstructed into a "live" logically linked network - an extra step that is often more trouble than it's worth.
This is not true for every software product, however - PMA's Netpoint, for instance, keeps the network logic live left of the data date!