Extention of Time of Power Plant Project

Dwi Jaka PrastyaMember for 14 years 5 months
Created
2
2
0

Dear all

 

I have some problem to solve and closing the contract of my project, my project already COD long time, and the project delay maybe 394 days from the amandment contract. can i propose EOT if the contract already have certificate for COD and TOC? thanks

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Dwi Jaka PratsyaProvide

    Hi Dwi Jaka Pratsya

    Provide your claim is not time barred by the contract or local jurisdiction you can present an EoT claim at any time.

    Best regards

    Mike Testro

  2. 0
    Dwi Jaka Prastya ·

    okey thank you mike  Best

    okey thank you mike

     

     

    Best Regards

     

    Dj Prastya