EOT Claim
- Created
- 7
- 1
Hi all,
In a remeasurable contract, can the contractor claim for EOT based on more work required during execution than planned. or a new basline(time) to be fixed accordingly, everytime the planned quantity changes?
For eg:
In the plan, there was 40LM of cable pulling. now during the execution it changed to 100LM and required more time to complete the work (assuming with the same resource as planned in baseline). This delayed the termination of cables, testing & commissioning etc and the contract completion date. can the contractor raise a claim for EOT?
Regards
Kannan
7 replies