Prolongation costs in case of pacing delays

Aqil MahmoodMember for 21 years 1 month
Created
3
2
0
Hi If a contractor decided himself to pace non affected work with ongong affected works, whether he would be eligible for prolongation costs? Or his delay in non affected areas woul be treated as concurrent delays that will not entitle him any prolongation costs? Regards

3 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi AqilExtension of time are

    Hi Aqil

    Extension of time are separate to claims for costs.

    Pacing will not affect an EoT award but it will be taken into account when assessing and prolongation / disruption costs as it is very difficult to prove pacing is not delay.

    Best regards

    Mike Testro

  2. 0
    Aqil Mahmood ·

    Thanks mike It means if

    Thanks mike It means if contractor hasnt provided advance notice to the client that he will be pacing his activities with employers delay event, this will be treated as his concurrent delay? Also could u plz advise me some good books on evaluating extension of time and prolongation costs. Many thanks
  3. 0
    Mike Testro ·

    Hi AqilI agree that a notice

    Hi Aqil

    I agree that a notice of pacing is good practice but it is rarely done.

    I would suggest my ebook - Principles of Delay Analysis - will give you a good insight into delay analysis procedures.

    It can be downloaded from my website www.expertdelayanalysis.com for £75.00

    Best regards

    Mike Testro

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?