Delay due to re-design
- Created
- 5
- 3
Dear All,
This delay happened in the mid of a project. After completion of a foundation there was a design change and additional floor to the building due the re-design and strengthening of foundation, some delay (due to abortive works @ 3months) happened. Now the situation is in such a mess that contractor has to revise the programme to include new scope and abortive works causing an overall delay of more than 6 months. Also some handed over areas again delayed due to additional soil stabilization works to be carried out by another contractor. How can be modify the Baseline inorder to incorporate all these changes ?
Your comments will highly appreciated.
Best Regards,
Sunil.