Delay Claim
In the Open Standard
Jithin KambhikanamMember for 15 years 6 months
- Created
- 5
- 1
0
Hello Everyone,
Please help me in learning about this topic regarding Claim. The situation is as expalained below
The days for project completion : 100
Delay from Contractor will push the completion days to - 130
Delay from Client will push the completion days to - 110
Both are parallel delays without which the project cannot be completed. so what will be the delay charge to Contractor 20 days or 30 days as the maximum delay is caused by the Contractor which is in parallel with Clients delay.