EOT Claim
- Created
- 4
- 1
Hi,
Due to a client delay causing event, we modified one of the schedule calendars and addedd a night sheeft into it as a sort of mitigation to avoid slippage on practical completion date. ( without any direct instruction from our client) By removing that night sheeft, we are entitel for about 10 days extension of time. Now, project is completed and we are working on our claims/ Just want to have your experience to know if we can claim that EOT by removing night sheeft from our calendar? ( it was not in our approved baseline schedule and has been addedd into our project schedule in one of the weekly update program as a sort of mitigation)
Thanks
4 replies