Skip to content

Preparation and Evaluation of Acceleration Schedule

Dimple DeanMember for 10 years 11 months
Created
2
3
0
Hi All,
 
Contractor agreed to submit acceleration schedule.
What I understand about the acceleration is if the project delay is 8 months, 
and if Contractor agreed to accelerate in 4 months, they need to compress the schedule from 8 months to 4 months.
If the Contractor agreed to submit acceleration, would it be from the current updated schedule and compress the schedule?
How to evaluate acceleration programme and costs that are associated with it?
 
Many Thanks!

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Dimple - Welcome to

    Hi Dimple - Welcome to Planning Planet.

    There is no point in putting acceleration measures on completed work so you must concentrate on work in progress.

    Take the current schedule that shows work to complete and take a histogram of the planned resources needed to complete the works in the 8 month duration. Set this data into a spreadsheet.

    Now you can concentrate on the acceleration methods - DO NOT just shorten each bar to achieve the result but concentrate on:

    1. Working Hours inc Overtime and Weekends.

    2. Changed work sequences - extra gangs deployment.

    3. Changed calendars - weekend working - multi shift working.

    All the time make sure that:

    4. The gang deployment is NOT overcowding a work zone.

    5. The crane and distribution kit can cope

    6. You have lighting in place for night work and your elecricity supply can cope

    7. Welfare facilities are adequate for the increased work force

    When complete run another histogram to set alongside the original to calculate the extra costs involved.

    If after all this you cannot see a 4 month result then DO NOT try to fix it.

    Best regards

    Mike Testro

    PS Don't forget that you cannot accelerate curing times unless you change the mix contents

  2. 0
    Dimple Dean ·

    thank you very much Mr. Mike

    thank you very much Mr. Mike

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?