Hi Everyone

Would notice legal and acceptable to the Employer / Board or a Court if a Contractor serves a notice to the Employer under FIDIC clause 20.1 for delay that has not yet occurred but likely to occur.

Cheers Tanveer

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi TanveerA timely notice of

    Hi Tanveer

    A timely notice of delay is always acceptable.

    Best regards

    Mike T.