Why "Fragnet"
In the Open Standard
Mike TestroMember for 20 years 10 months
- Created
- 3
- 3
0
Good Morning Analysts
I dislike the term "Fragnet" used by some analysts to describe a series of events inserted into a barchart to represent delaying events.
Why Fragnet - is it supposed to a connection of "Fragmented Network"? If so then why so?
I suspect that the term is meant to make the analysts art even darker - in which case it should be banned.
I agree that the process is sound which is why I place the delaying events into a Sub-Chart - even a Judge can understand that plain English.
Best regards
Mike Testro