Skip to content

Time claim filter problem

Yalçın GünerMember for 11 years 5 months
Created
12
3
0
Hi, all
 
I'm sorry my spelling mistakes. I am not god at english
 
I am going to filter my special activity's all successor chained by to each other but I didn't find anyway
 
For example I should remove my fancoil activity and all successor's(path) aktivities actual start from p6
 
How can I do using global change to filter all of this activities at once and check off their actual start to link all of them delay activity's successor.

12 replies

Oldest first
  1. 0
    Gordon Aronson ·

    I will first apologize for

    I will first apologize for possibly misunderstanding your question.

    My immediate thought is that you need a good/complete set of activity codes so that you can filter/select activities that are all part of a common process like those that are predecessors to Fan Coil Install (that support this activity's readiness.  Then you can easily select only those activities and work only on those activieies.

    If I went in the wrong direction, please do your best to further explain.

    Gordon

  2. 0
    Vladimir Liberzon ·

    In Spider Project there is

    In Spider Project there is standard filter: show all successors of current activity. I expect that something like this may exist in P6.

  3. 0
    Mike Testro ·

    Hi VladimirIn Asta there is

    Hi Vladimir

    In Asta there is an icon that will show all predecessors and successors of a selected task. You chose driving links only to get a clear picture.

    Best regards

    Mike Testro

  4. 0
    Vladimir Liberzon ·

    Mike, does Asta filter and

    Mike, does Asta filter and show all paths of successors and predecessors or just directly linked activities?

  5. 0
    Mike Testro ·

    Hi VladimirIt shows all tasks

    Hi Vladimir

    It shows all tasks linked upstream or downstream of the selected task.

    It is clearer using the "driving link" option.

    Best regards

    Mike Testro

  6. 0
    Vladimir Liberzon ·

    Thank you Mike!Filtering

    Thank you Mike!

    Filtering driving links as an option is useful, but to know all activities dependent on selected is useful too.

    Regards,

    Vladimir

  7. 0
    Rafael Davila ·

    On resource leveled schedules

    On resource leveled schedules if the resource dependencies are not disclosed you will be missing some relevant activities down/up stream.

    Make sure your software can disclose resource dependencies.

    http://www.ce.berkeley.edu/~ibbs/BRICS/Materials/Nguyen_Ibbs_DelayAnalysis_2006.pdf

    - Apportionment of delay responsibility may be inaccurate unless resource allocation practice is considered in the analysis.

  8. 0
    Yalçın Güner ·

    My schedule has approximately

    My schedule has approximately 8000 activities. I cant use activity codes because fancoil activity's has lots of paths included finishing works like suspended ceiling frame. I need to choose all of successors chained by each other. I hope you understand me correctly. Our fancoil installation was revised by the main contractor so I need to prepare our time claim analysis via p6
  9. 0
    Rafael Davila ·

    Usually a filter along with a

    Usually a filter along with a links table can be better for this purpose but in their lack you might try "trace logic".

    If your schedule is impacted by resource leveling the temporary links used by P6 will not be visible as it cannot disclose them. I use software that discloses the temporary dependencies but maybe you can figure out a methodology. I suppose you can identify resource delayed activities if they show no single driving logic predecessor.

    http://primaveratrainingblog.mssprojectsanalytics.com/how-to-use-trace-logic-in-primavera-p6/

    Good Luck

  10. 0
    Rafael Davila ·

    Executing the filter no

    Executing the filter no matter if pre defined or created this shall be available at a single click of the mouse. After  you execute the filter then deleting the links shall also be at a single click of the mouse. As easy as 123.

    For more complex filter on links the filter might have to be executed on the links table after initial filter on activities successors/predecessors/both. For this purpose using reports instead of filters on complex jobs is not efficient and is also error prone.

    As a double check and for documentation it is convenient to compare link tables among the versions, unfiltered vs filtered.

    LF01 photo LF01_zpsdytguxcw.png

    LF02 photo LF02_zpsdnoymr82.png

  11. 0
    Yalçın Güner ·

    May I import my xer file to

    May I import my xer file to do your advice in asta power project? 

  12. 0
    Mike Testro ·

    Hi Yalcyn. Yes if you have

    Hi Yalcyn. Yes if you have both sets of software. Just open the .xer file in ASTA. Best regards Mike Testro.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?