Multiple contract milestones

Alan TaylorMember for 9 years 3 months
Created
1
4
0
The contract contains multiple unit completion penalty milestones which are waived if the final completion milestone is achieved. The project is in serious delay. The contractor has submitted an EOT claim (TIA and owner delay events only) that is focused on delay to final completion milestone and ignores all the intermediate penalty milestones. In my opinion all penalty milestones should be included in the analysis - any comments please.

1 reply

Oldest first
  1. 0
    Mike Testro ·

    Hi AlanYes they

    Hi Alan

    Yes they should.

    Instruct your contractor to impact his dely events on the tasks leading to the milestones and refuse to consider anything else until it is done.

    Best regards

    Mike Testro