MSP negative float and constriant
In the Open Standard
V KuttyMember for 15 years 9 months
- Created
- 1
- 2
0
Hi,
I was analysing a schedule for a contractor. The final milestone (constrained finish on or before) has a float of -78 days and a finish of 1 Jan 15. If I remove this constraint I was expecting the end date to move by 78 days to Middle of March. Instead the program moved by 152 days. Any idea why this may have happened?
Thanks,
Regards,
Vijay
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?