Skip to content

Extension of time

Bialla RafiqMember for 9 years
Created
5
2
0

Dear Mr Zoltan

I need some advice on below scenario

We have project having milestones

One of the Milestone is installation works, we have an extension of time earlier due to employer delays.

Currently that work supposed to be finish in June, 2017 however we unable to complete the works by the extended date of the milestone. 

As of October, 17 - we are still working on milestone.

In August - employer gave us access to one of the sub milestone activities which supposed to be earlier as per approved baseline programme. And this work in progress parallel to our works which we supposed to finish but not completed.  

Shall the employer delay are concurrent delays in this above case. Any case law reference document will be much appreciated. 

 

Thanks 

Bilal Rafiq 

5 replies

Oldest first
  1. 0
    Mike Testro ·

    I will let Mr Zoltan answer

    I will let Mr Zoltan answer this.

  2. 0
    Bialla Rafiq ·

    Dear Mike You can also

    Dear Mike You can also advise , what is your consideration on this . Delays which appear after the contract Mileatones as explained in above scenario. Thanks Bilal
  3. 0
    Mike Testro ·

    Hi BiallaConcurrency is

    Hi Bialla

    Concurrency is complex and a lot depends on the jurisdiction where the work is and the law governing the contract.

    Last week in the UK a case settled the position in the UK and we are back to the dominant delay situation.

    In most of the rest of the world they follow an apportionment system.

    On this basis if the total delay was caused by a contribution form each party of 50% each then their would be 50% LAD's and 50% Loss and expense.

    In the UK if the contractor has caused the dominant delay then he gets all the LAD's and no Loss and expense.

    If the employer delay is domnant then it is the overlap that counts with the Contractor getting Loss &Expense for the end bit and no costs for for the rest.

    Best regards

    Mike T.

  4. 0
    Bialla Rafiq ·

    Dear Mike Thanks for your

    Dear Mike 

    Thanks for your response, in Middle east we donot have any law refer to dominat cause /apportionment system.

    Now i our project senario - contractor unable to complete the work as per the Milestone completion and also employer did not allow us to work on some part of the work .

    So mostly we discuss whether this was is critical or not- so my understanding is if the works not completed as per the contract dates then its critical for Milestone completion as its already expired- IS THIS TRUE?

    Second, please advise if the Empoyer delay appear after expirty of contract Milestone finsih date and contractor finish those works approximate same time period-  It means the effect of both delays are same- and should be considered same. IS THIS TRUE 

    Please guide on this. 

     

    Thanks Bilal Rafiq 

  5. 0
    Mike Testro ·

    Hi BiallaBut you do have the

    Hi Bialla

    But you do have the Unjust Enrichment clause in your code which means that no party can gain any benefit from his own default.

    Besr regards

    Mike T.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?