Contemporaneous and Forensic Time Impact Analysis

Shahin DshMember for 8 years 6 months
Created
4
2
0

hello experts

I'm confused about differences between "Contemporaneous Time Impact Analysis" and "Forensic Time Impact Analysis". can anyone explain me what are the differences between these two topic?

4 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Shahin Contemporaneous

    Hi Shahin Contemporaneous time impact analysis is when work is still in progress. Forensic Time Impact Analysis is when work is complete.
  2. 0
    Shahin Dsh ·

    Hello Mike thanks for your

    Hello Mike 

    thanks for your reply. but is that the only difference? i mean does calculating the claimable time differes in these two methods?

  3. 0
    Mike Testro ·

    Hi ShahinThere is essentially

    Hi Shahin

    There is essentially no difference except that your access to As Built data is limited when work is in progress.

    Best regards

    Mike T.

  4. 0
    Pei Tang ·

    Hi Shahin,I will try to

    Hi Shahin,

    I will try to explain from what I understand. 

    When you performing a delay analysis for events, there are two situations:

    1) the delay events are happening or going to happen , and your objective is to ESTIMATE the impacts from the delays so that the contractor and owner can make new agreement. This analysis is often performed while the project is in progress. AACE defines it as propsetive time impact analysis  and you can find a guide from their website. 

    2) the delay events have happend already, and your objective is to Quantify the delays and Identify the Responsiblity by using actual data. Most of time  this analysis is defined as "Forensic Time Impact Analysis" or "Retrospective Delay Analysis" because the impacts have already happened. This anlaysis is usually performed after the events happend or after the project is completed.

    There are lots of methods for "Forensic Time Impact Analysis", and "Contemporaneous Time Impact Analysis" is just one of them which uses contemporaneous schedules (approved baseline, approved updates, and if really needed adjusted baseline and updates as well). 

    I hope it helps.

    Best regards,

    Pei