Recovery Schedule and EOT Claim Analysis
- Created
- 5
- 3
Hi All,
As specified in Fidic Contracts, if the Contractor failed to meet the progress rate as agreed in the approved Baseline Schedule, he needs to submit a recovery schedule, elaborating how he intends to recover his delays and bring the Project back on track.
1. Is the Recovery Schedule to be approved, or just to accept it based on the Contractor's revised sequence/methodology/additional resources etc, for the progress monitoring purpose?
2. If any new claims araised (after this recovery schedule), which schedule to be followed for the EOT analysis- original approved baseline or the approved/accepted recovery schedule?
3. Is there any accepted guidelines like SCL Protocol, which specifies which schedule to be followed?
BR
Kannan
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?