Extension of Time (Bad weather condition )

Arun VasanthMember for 17 years
Created
3
4
0

Dear All

There was a work stoppage for 3 days due to bad weather and it took 3 days to back to the normal condition.

Client Intent to give an extension of time for 3 days without cost but the updated program showing no delays.

Is the contractor eligible for the Extension of time ???

 

Regards

Arun.V

3 replies

Oldest first
  1. 0
    Santosh Bhat ·

    Whether they are entitled or

    Whether they are entitled or not, is written into the contract, not the program. The program is the tool used to demonstrate the value of the entitlement, if such exists.

    The conctract  will also specify the method that must be used to demonstrate the impact of the delay, how and when it must be communicated.

  2. 0
    Mike Testro ·

    Normally any extension of

    Normally any extension of time for weather must be on the basis of it being exceptionally inclement.

    In other words worse than expected.

    Expected wetaher delays should be built into the programme on the basis of Non Work days in the calendar.

    If the contractor hasn't done so then the actual weather stoppage could be used as a way of reducing a claim 9of whatever cause) when it arises

  3. 0
    Mike Testro ·

    Hi ArunBeware of a contract

    Hi Arun

    Beware of a contract which limits the method of claiming an EoT.

    If that method does not work and an eoT claim is impossible then time would be set at large.

    Best regards

    Mike Testro