Owner caused delay - most basic cost %?
In the Open Standard
John ReevesMember for 13 years 5 months
- Created
- 3
- 2
0
Ok, so there is an owner caused delay, say it is 30 days. So the Contractor gets a 30 day time extension and what % of Gen. OH costs = 4%, 6% of contract value - what is the general rule of thumb? I know there are 10 ways to calc it, what is most simple? what is most common? If there was a cost loaded schedule, couldn't they supercede that simply because accounting has better numbers or industry precedence?