Aren't "windows" delay analysis flawed by the common condensing of schedule as schedule goes on?
In the Open Standard
John ReevesMember for 13 years 5 months
- Created
- 2
- 5
0
Aren't "windows" delay analysis flawed by the common condensing of schedule as schedule goes on? - Do if the project is complete and you have 5 delays at 20 days each, but he job is only 20 days late - couldn't you just prorate each delay - because none should get credit for other changes to bring it back onto "close to" schedule?
2 replies