Final EOT Entitlement Calculation

Mohamed BasheerMember for 17 years 3 months
Created
1
4
0

As per the delay anaysis total 4 months delay happened. Contractor is responsible for 3 months and owner responsible for 1 month. 

Is contractor entieled for time extension for this 1 month delay by owner.

How to calcuate final delay assessment after the cases like this?  

1 reply

Oldest first
  1. 0
    Mike Testro ·

    Hi MohamedIf you are talking

    Hi Mohamed

    If you are talking about overlapping delays the usual rule is that you will be awarded an EOT but no prolongation costs.

    But the contract that you signed may not allow this.

    Best regards Mike T.